Anyinam By-pass (Accra–Kumasi Highway)
Ongoing75% complete
About this project
Construction of dual carriageways bypassing Anyinam on the Accra–Kumasi Highway. The south-bound carriageway (6.10km) was 57% complete and the north-bound carriageway (6.10km) was 93% complete, as of the 2025 Budget Statement (status as of December 2024).